BELMONT – Mar 2018

We want to thank all your builders for rescheduling the Belmont Open Day until after Easter and hope we have better weather this time around. If you are interested to have a look at your block yourself, it is possible to book a separate inspection time with our sales office to check out the progress. Please call 1300 289 733 to organise your inspection time.

The landscaping works are progressing well in Belmont. Open space landscaping is nearing completion. Timber post and rail fences are up, turf has now been laid around the dam and it looks amazing! The rain last week definitely helped establish the newly laid landscaping. The large entry statement signage for Belmont is now being fabricated off-site to be installed soon. We will post artist impressions on Facebook next week but are sure that you will like them as much as we do.

Authorities continue to commence their process for connection of utilities in Belmont. Sydney Water preferred contractor Diona is now working inside the Sydney Water compound to carry out the electrical and overall water infrastructure upgrade works, and sub-contractor Jonishan is finalising the sewer connection, which both are vital for registration. Our project delivery team is working on preparing subdivision certificate for lodgement which will be lodged with Council as soon as we receive the final sign off from the authorities.

As noted in previous newsletters, when authorities complete their process of inspections and acceptance of their services, Council will issue the Subdivision certificate. The process after that are your lenders approval, lodgement to LPI and actual settlement.

Please refer to the indicative flow chart that explains this process and estimated timelines. It can be found at:
http://www.redbankrichmond.com.au/redbank/_asset/img/Resources/All_Stages/Activity_Flow_chart_RevB.pdf

We highly recommend not getting into a building contract till the announcement of registration. By law, our lawyers will have to contact your solicitors to notify them about settlement. We will keep you updated every step of the way through Facebook and email and you will have enough time to get prepared with your funding and locking in a builder.

We now have uploaded the Geotech site classification report on our “Building at Redbank” tab on the website. Please see link below:
http://www.redbankrichmond.com.au/redbank/_asset/img/Resources/Belmont/Belmomt_Geotech_7747-34A_A_Site_Classification_Report.pdf