Community News

Related Newsletter : March, 2018
Category : Project Updates

THE GALLERY – Mar 2018

Great news for The Gallery owners! Two houses in The Gallery have received their occupational certificates this week. The two families have already moved in as well. We know that more OC-s are being signed today and next week. We are really excited for all of you, and cannot wait to officially welcome you to the Redbank family once you move in.

14 Houses in The Gallery are now in the defect checking process in electrical, plumbing and other areas and occupancy certificate inspections will continue to be coordinated by the site supervisor.
Stage one landscaping is now nearing completion and the sub-contactor has already started working on stage two. The footpaths and streetscaping has also begun and you will see it taking shape in the coming weeks.

MJH has completed 32 driveways till date and only eight roofs are remaining to be installed for the entire precinct.

21 homes on stage 2 are now in Gyprock and carpentry stage and they are expected to be completed soon. Joinery works is now finished in all stage one homes and commenced on 12 homes in stage two. Metal awnings are almost completed in stage one and ten percent done in stage two.

MJH has requested all buyers not to access their homes till delivery. It is still a construction zone and there are severe health and safety risks in attending the site without proper induction and supervision.

If you have any questions regarding your new home, please contact Elif Kaplan via email at kaplan@mjhmulti.com.au or on 02 8808 7467.